Latest CNS/ATM Information

a. North ATS Park: The Electrical Machinery and the Air Condition maintenance contractor

    moved into the North ATS Park on 1 July 2008. The Aviation Police also moved into the

    North ATS Park on 1 July 2008. The ANWS took possession of the North ATS Park on

    10 July 2008.

b. South ATS Park: The license to operate the South ATS Park was obtained on 13 June

    2008. The ANWS finished the final check of the South ATS Park on 22 July 2008.

c. The Air Traffic Control, FIS and CNS Cadre instructors were sent abroad to the

    contractor factories in stages to receive system operation and maintenance trainings

    from 28 July 2008 to 19 Sep 2008. All the ATMS and AISS factory trainings were

    completed by 19 September 2008.

d. Seminar on Global CNS and ATM Technologies and Trends was conducted from 18 Aug

    2008 to 20 Aug 2008。

e. Regarding the ATMS subsystem “Radar Signal Transmitting and Receiving Bridging

    Server” (contract number RCOM-20080716) procurement, the contractor completed the

    equipment delivery on 3 Sep 2008. ANWS is preparing for the equipment Acceptance.

f. ANWS has completed the training of the Global Positioning System (GPS) Receiver

    Autonomous Integrity Monitor (RAIM) Prediction System (RPS) on 30 July 2008 and the

    RPS Site Acceptance Test on 1 Aug 2008. ANWS will submit a Proposal for RAIM

    NOTAM (used to be GPS NOTAM) operations before 30 Sep 2008. (The RPS contract

    is estimated to be completed by end of 2008)